Page 64 - GM's Annual Inspection Booklet DEC- 2022
P. 64

Divitipalli  (Pt.No.105B&102B),  Poodoor(Pt.No.7B&13B),  Mirzapalli  (Pt.No.8B,13B  &
                    14B),  Gadwal  (Pt.No.11B,12B,19B  &  20B),  Kacheguda  (Pt.No.14A,15B&17B)
                    Talamadla (Pt.No.7B& 13B) and Mirzapalli (Pt.No.7B).
































               4.  Gate holding arrangements for LC gates located between LSS & Home signal provided
                   at 12 LC gates: 196 atDichpalli, 198at Indalvai,180at Dharmabad,18JBat Bodhan, 155
                   at Veldurthi, 98 at Gadwal, 138at Dupadu, 73 at Devarakadra, LC gates: 165 at Umri,
                   198 at Dichpalli, 209A at Kamareddy, 155 at Veldurthi. With these all the identified 12
                   LC gates in the division completed.

               5.  In connection with Railway Electrification works, the following works commissioned by
                   RE/SC organization:

                        a.  Energisation  of  conventional  OHE  with  25KVA  carried  out  between
                           Manoharabad  -  Kamareddisection  on  27.10.22  and  Mahabubnagar-Gadwal
                           section on 27.11.22.
                        b.  Existing  PTJ  single  line  tokenless  block  instruments  replaced  with  UFSBI  of
                           M/s  Deltron  make  and  HASSDAC  of  M/s  GGtronics  make  in  the  above
                           sections.(Total 12 block sections)














               6.  Commissioned  provision  of  sequential  Route  release  of  UP  &  Dn  calling  on  signals
                   S40A and S1A.