Page 189 - GM booklet 2019 test
P. 189

Energy Conservation Measures Taken

                                                           For the Month of       Cumulative for the Year
                                                                Oct-19                  2019-2020
                Sl.                             In
               No            Item           Numbers      Capacit    Anticipate   Capacity      Anticipated
                                                                    d Annual
                                                                                                 Annual
                                                            y
                                                                     Savings                    Savings
               1     Solar Panels                                                     -             -
               2     Solar pumps                -           -            -            -             -
                     Solar Water                                                               Rs.30000/-
               3                                                                 1000LPD
                     Heaters                                                                     approx
                     100% LED lit
               4                           100% completed
                     Stations
                     100% Led Lit
               5                           100% completed
                     Service Buildings
                     Natural Day light
               6                               -          -             -           -             -
                     pipes installed
                     Hybrid Plant
               7                               -          -             -           -             -
                     (Solar+Wind)

               Housekeeping activity at NZB station:

                             Firm: M/s SK enterprises, Secunderabad
                              Period: 20.01.18 to 19.01.20

                             Cost : Rs. 73,87,606.00/-
                             Average Manpower per shift:  06 to 14 hours : 10 workers
                                                                    14 to  22 hours : 7 workers
                                                                    22 to 06 hours : 1 worker
                             Important Machineries used:
                                Cold Water High Pressure Jet
                                Electrically operated Walk Behind automatic scrubber drier
                                Single disc floor scrubbing machine
                                Ride on sweeping machine (battery)

                                Wet & Dry vacuum cleaner
                                Manual sweeper with in built manual vacuum system

               Housekeeping activity at BSX station:

                             Firm: M/s SK enterprises, Secunderabad
                             Period: 02.08.17 to 01.08.19  (extend for 6 months upto 01.02.20)
                             Cost : Rs. 22,12,704/-
                             Manpower per day: 7
                            Important Machineries used: Flipper walk behind sweeping machine
                                                                                 (Manual)