Sl. Description of work Year of Anticipate Status
No Sanction d Cost
1. Provision of New crossing 2010-11 Cap Works in progress.
station at Pedashapur 16,95,00
between
Umdanagar&Timmapur on
SC-MBNR section.
2. Provision of 04 new 2017-18 38,26,00 1. Work in Progress for Bridge &
crossing stations. Earth Work. Land Acquisition for
Station Building under Process by
1. Wanaparthy-Kaukuntla State Govt. of Telangana (3
(18.27 kms) Stations) & Andhra Pradesh (01
2. Monopad-Alampur Station).
(16.10 kms) 2. Exemption received for 01 Station
(Perur) between WPR-KQQ. At
3. Itikiyala- Monopad present only one station is planned
(13.58 kms) between WPR-KQQ (Perur station)
and remaining 03 stations will be
4. Ulindakonda- Veldurthi taken along with doubling.
(12.06 kms)
TDC- 31.03.2021
3. Nizamabad: Remodelling 2018-19 8,79,84 CRS sanction obtained, Agencies
of yard arrangements for Available, Work not started due to
providing additional involvement of shifting of Goods shed
platforms and one full to JKM station. Proposal for shifting
length dead end spur. of Goods Shed to JKM and
development of goods shed
circulating area at JKM is pending for
sanction at Railway Board. TDC
30/03/2023
4. Jankampet Jn: Additional 2019-20 11,30,00 The work was proposed under PWP
two loop lines. 2019-20 and approved by GM under
5. Falaknuma: Standard double 2019-20 8,57,00 Umbrella works.
line layout by provision of Railway board accorded sanction on
DN loop line (standard 29.09.2021.
double line layout) Necessary ESPs to be prepared.
6. Talamadla: Additional loop 2019-20 6,37,00 The work was proposed under PWP
line (standard layout). 2019-20 and approved by GM under
7. Sirnapalli: Additional loop 2019-20 6,37,00 Umbrella works and sent to Railway
line (standard layout). board for approval.