            SANCTIONED WORKS

            PRELIMINARY WORKS PROGRAMME (PWP) UNDER TRAFFIC FACILITIES
            (PH: 1600)
                                                                                           (Rs. in 000‟)
          Sl.       Description of work          Year of     Anticipate                    Status
          No                                    Sanction       d Cost
           1.  Provision of New crossing         2010-11         Cap       Works in progress.
                station at Pedashapur                         16,95,00
                between
                Umdanagar&Timmapur on
                SC-MBNR section.
           2.  Provision of 04 new               2017-18      38,26,00     1. Work in Progress for Bridge &
                crossing stations.                                            Earth Work. Land Acquisition for
                                                                              Station Building under Process by
                1. Wanaparthy-Kaukuntla                                       State Govt. of Telangana (3
                  (18.27 kms)                                                 Stations) & Andhra Pradesh (01

                2. Monopad-Alampur                                            Station).

                     (16.10 kms)                                           2. Exemption received for 01 Station
                                                                              (Perur) between WPR-KQQ. At
                3. Itikiyala-   Monopad                                       present only one station is planned
                   (13.58 kms)                                                between WPR-KQQ (Perur station)
                                                                              and remaining 03 stations will be
                4. Ulindakonda-    Veldurthi                                  taken along with doubling.
                   (12.06 kms)
                                                                              TDC- 31.03.2021
           3.  Nizamabad:  Remodelling           2018-19       8,79,84     CRS  sanction  obtained,  Agencies
                of yard arrangements for                                   Available,  Work  not  started  due  to
                providing additional                                       involvement of shifting of Goods shed
                platforms and one full                                     to  JKM  station.  Proposal  for  shifting
                length dead end spur.                                      of  Goods  Shed  to  JKM  and
                                                                           development       of    goods      shed
                                                                           circulating area at JKM is pending for
                                                                           sanction  at  Railway  Board.  TDC
                                                                           30/03/2023
           4.  Jankampet Jn: Additional          2019-20      11,30,00     The work was proposed under PWP
                two loop lines.                                            2019-20 and approved by GM under
           5.  Falaknuma: Standard double  2019-20             8,57,00     Umbrella works.
                line layout by provision of                                Railway board accorded sanction on
                DN loop line (standard                                     29.09.2021.
                double line layout)                                        Necessary ESPs to be prepared.
           6.  Talamadla: Additional loop        2019-20       6,37,00     The work was proposed under PWP
                line (standard layout).                                    2019-20 and approved by GM under
           7.  Sirnapalli: Additional loop       2019-20       6,37,00     Umbrella works and sent to Railway
                line (standard layout).                                    board for approval.