23. Party vide letter dated 06.07.2018, disputed the Land Rate adopted for the calculation of
                Land License Fee payable to Railways and requested for revised calculation adoption of
                land rate under Dry Land Class rate.
             24. Reply  given  to  party  with  regard  to  dispute  in  calculation  of  Land  License  fee  on
                01.11.2018.
             25. Charges of railway land licensing fee communicated to party vide Sr.DEN/Co-ord, letter
                No.YW/277/W.V/Pvt.Siding/Jankampet/18 dated 04.12.2018. (Reminder)
             26. From 06.07.2018 to 18.06.2019 correspondence on Land Rate Disputes had happened.
                During this process, division tried to obtain nearby land rates from Sub-Registrar Office.
             27. On 09.09.2019, a note was initiated for revision of Land License fee based on the land
                rates which were obtained from sub-registrar office on 03.07.2019.
             28. Revised  Land  License  approved  by  competent  Authority  DRM/HYB  and  “In-Principle
                Approval” obtained on 22.10.2019.
             29. Charges of railway land licensing fee communicated to party vide Sr.DEN/Co-ord,
                Lr.No.YW/277/W.V/Pvt.Siding/Jankampet/18 dated 21.01.2020 as per New GST Policy.
             30. Charges of railway revised land licensing fee communicated to party vide Sr.DEN/Co-ord,
                letter No.YW/277/W.V/Pvt.Siding/Jankampet/19 dated 29.11.2019, 06.02.2020, 17.03.2020
                & 11.05.2020
             31. Party has remitted the land license fee with security deposit to railways on 12.05.2020,
                GST paid on 27.11.2020 and GST payment particulars submitted on 27.11.2020.
             32. Draft  agreement  was  sent by  Engg  branch to  Accounts  department  on  10.03.2021 and
                obtained finance vetting on 29.04.2021 with observations.
             33.  Clarification was sought on GST to be paid by Party, as party is not registered under GST
                 Act and clarification on GST received from accounts branch on 28.05.2021.
             34. On 03.06.2021, Engg. Branch advised party to apply and register under GST to obtain
                GSTIN and to submit at the earliest for further process of entering into the Land Licensing
                Agreement.
             35. Based on the remarks of Accounts branch, agreement is prepared by Engineering branch
                and sent to Law branch on 07.06.2021 for obtaining legal vetting before executing the land
                license agreement with the party.
             36. Land  License  Agreement  was  executed  with  the  party  on  06.07.2021  for  sparing  of
                Railway Land admeasuring 38800.48 Sq. Yrds. (32441.8768 Sq. Mtrs)
             37. Work yet to be started by the party but siding owner not responding to M/s S4 Projects
                Infra Pvt. Ltd. consultancy.