              1   Lakshme food processing ware house & cold storage taking off from                  Private
                  Jankampet Jn. station on NZB-MUE section.

                Remarks:
             1.  The DPR/ESP of the subject siding proposal was approved on 03.08.2012.
             2.  Draft  agreement  was  sent  by  Engg  branch  to  Accounts  department  on  12.12.2013  for
                obtaining finance vetting.
             3.  Legal vetting obtained on 06.01.2014.
             4.  On  07.02.2014  Party  laid  a  Kachcha  road  with  unauthorized  boundary  wall  in  Railway
                land without any permission at KM 450/4-9. Same informed to IPF/NZB.
             5.  On  20.02.2014,  Division  has  advised  to  Headquarters  regarding  the  inescapability  of
                railway land and an alternate alignment which will account for less extent of land to be
                leased. Hence, advised to change the proposal and submitted accordingly.
             6.  As  per  approved  ESP,  1.6  KMs  lead  line  is  in  Railway  land.  On  11.04.2014  Division
                advised to CGE/SC that only 300mtrs X 11mtrs of Railway land can be spared.
             7.  Informed to Party about non-feasibility for loading/unloading activities at JKM and advised
                to utilize NZB goods shed for the same on 02.07.2014.
             8.  On 15.102014 & 11.11.2014, consultant on behalf of the party requested for grant of Way
                Leave facility. Same was not permitted by Head Quarters.
             9.  On 02.12.2014, a Writ Petition No.38772 of 2014 case filed by Party.
             10. CTPM/SC‟s  Lr.  No.T.143/Y/316-Vol-I  dated  07.08.15  has  sent  revised  DPR  and  Paper
                Tracing plan, submitted by consultants, for approval of Division.
             11. Based  on  S&T  branch  remarks,  submitted  a  letter  to  CTPM/SC  on  09.10.2015  in
                connection with change of takeoff point from Loop line instead of Main line.
             12. Court case withdrawn and disposed on 15.12.2016.
             13. Party requested for Land Licensing proposal on 27.07.2017.
             14. Party informed about withdrawal of court case on 25.09.2017.
             15. Party  obtained  land  rates  from  Sub-Registrar  office  of  survey  no.  986  &  1046  on
                02.11.2017 and submitted to this office.
             16. Engg. branch advised party to submit Survey plan on 06.11.2017.
             17. Party submitted survey plan on 09.11.2017.
             18. A note was initiated on 01.01.2018 for approval of DRM as per Model SOP (Part-A (53)
                Sl. No.44) for sparing of Railway land.
             19. DRM raised a question regarding reason for increase in Land requirement from 3500 Sq
                Mtrs to 32441 Sq Mtrs on 06.02.2018.
             20. Explanation given by Engg Branch during April-2018.
             21. DRM approved the same for sparing area of Railway Land on 23.04.2018.
             22. Land  license  fee  calculation  was  prepared  and  advised  to  party  for  the  payment  on
                09.05.2018.