Page 32 - OPERATING
P. 32
New lines:
1) Akanapet – Medak (17.20 Kms):
Work sanctioned vide PB 2012-13.
The ESPs of Akanapet and Medakwere approved and works is in progress. All Tenders
for 17.20 Km has been finalized and targeted for commissioning during 2020-21.
NI work done from 14.05.2019 to 18.05.2019 (3 days PRE NI and 02 days NI) at
Akanapet and additional loop line was commissioned on 08.05.2019.
2) Manoharabad – Kothapalli (148.90 kms):
Work sanctioned vide PB 2006-07.
Manoharabad - Gajwel (30.10 KMs) commissioned on 19.06.2020 under 'One train only
system'.
3) Mahbubnagar – Munirabad (222 kms):
Work sanctioned vide PB 1997-98.
Phase-I works: DKC to KSN Works between DKC to JKAR section completed and one
train only system introduced on 25.03.2017.
CRS Authorization for new line extension between JKAR to MKTL commissioned on
05.06.2020 under „ONE TRAIN ONLY SYSTEM‟.
The works between MKTL to KSN is in progress.
Assistance Required:
Up-gradation of CC+6+2(T) to CC+8+2(T) route between SC-DHNE section and Bypass
lines between MLYG-MJF & STPD „A‟ & „B‟ cabins.
Janakampet (JKM) yard remodeling work along with goods shed for alternate goods
shed for Nizamabad sanctioned under PWP.
Early commissioning of Gajwel and Medak goods sheds in order to capture the freight
traffic from Medak and Siddipet districts.
Electrification of Manoharabad-Nizamabad of SC-MUE section is required as first priority.
The existing line between STPD-A & STPD-B cabins is single line(0.7 km0 to be
provided with doubling.
CSRs of Road 3,4 & 5 at KCG station to be increase to 715 m in order to facilitate full
length trains and pass MMTS trains via main line without any delay.
Page 32 of 35