3. Progress of Through Rail Renewal (P) and Through Sleeper Renewal Works.


                                             2020-21
                      Item                       Progress up to                  Remarks
                                   Target
                                                    Feb 2021

                                                                      1.04  Tkm  Rails  (20  RP)
                     TRR (P)       07Km              5.93 Km          received  and  unloaded  on
                                                                      23.02.2021.
                     TSR (P)       05  Km             05 Km           Target achieved.



            4. Reduction in Asset Failures

                 Rail / Weld failures -   Division has achieved a reduction of 41 % over last year, In

                   the year 2020-21 Rail / Weld failures are10 Nos (Up to Feb‟21) compared to 17 Nos
                   in the year 2019-20 (Up to Feb‟20).


            5. Relaxation of Permanent Speed Restrictions.

                 Target 2020-21 = 02
                 Progress = 02

                                 Existing PSR
                                                                                        Remarks
            Sl     Km       Section         SR            Reasons
           No
                                                                          Relaxed to 100 Kmph in Jan‟2021
                 218/0-    IKI-MOA-                   Consolidation of  (Caution order of 04 Kms length
           01                            75 Kmph
                  222/0      ALPR                           Track         has been made as caution order of
                                                                          01 Km length)

                 491/0-                                 4 D curve in      Relaxed to 75 Kmph in Feb‟2021
           02              UPW-SCP       60 Kmph
                  492/0                                 Ghat section

            6.  Through  formation  Treatment  with  Moorum  Blanketing:  The  work  of  Through
            Formation  Treatment  is in  progress  in  SC-MUE  section  and  a  progress  of  7.910  Km has
            been achieved till end of Feb‟21.

















                    Through Formation Treatment work on SC-MUE section between DAB-KEK stations