3. Progress of Through Rail Renewal (P) and Through Sleeper Renewal Works.
2020-21
Item Progress up to Remarks
Target
Feb 2021
1.04 Tkm Rails (20 RP)
TRR (P) 07Km 5.93 Km received and unloaded on
23.02.2021.
TSR (P) 05 Km 05 Km Target achieved.
4. Reduction in Asset Failures
Rail / Weld failures - Division has achieved a reduction of 41 % over last year, In
the year 2020-21 Rail / Weld failures are10 Nos (Up to Feb‟21) compared to 17 Nos
in the year 2019-20 (Up to Feb‟20).
5. Relaxation of Permanent Speed Restrictions.
Target 2020-21 = 02
Progress = 02
Existing PSR
Remarks
Sl Km Section SR Reasons
No
Relaxed to 100 Kmph in Jan‟2021
218/0- IKI-MOA- Consolidation of (Caution order of 04 Kms length
01 75 Kmph
222/0 ALPR Track has been made as caution order of
01 Km length)
491/0- 4 D curve in Relaxed to 75 Kmph in Feb‟2021
02 UPW-SCP 60 Kmph
492/0 Ghat section
6. Through formation Treatment with Moorum Blanketing: The work of Through
Formation Treatment is in progress in SC-MUE section and a progress of 7.910 Km has
been achieved till end of Feb‟21.
Through Formation Treatment work on SC-MUE section between DAB-KEK stations
20