iii.  BCM  290  machine,  which  is  working  in  the  Division  is  a  30  Yrs  old  machine.  The
                   progress achieved by the machine is about 67 Km in 10 Months, which is the highest
                   ever progress in the History of working of BCM-290 machine.

               iv.  During  lockdown  period,  when  passenger  carrying  train  traffic  was  less,  the
                   opportunity of traffic blocks was utilized and long pending work of Deep Screening in
                   suburban section i.e SC-FM and SC-BMO sections was taken up and completed.


                 Rebuilding of Br no: 74 on SC-DHNE section –

            The work of Rebuilding of Br No: 74 in UR yard on SC-DHNE section has been taken up
            duly taking a mega block of 64 Hrs i.e from 08.00 Hrs of 16.05.20 to 00.00 Hrs of 19.05.20.
            (This work is executed by RVNL as a part of Doubling of SC-MBNR section)























                                                              Rebuilding of Bridge no. 74 in UR yard.

            Note: This work has resulted in saving of Rs 10 Crores to  Railways, as it is
                       executed by RVNL as a part of SC- MBNR doubling work.

                 Rebuilding of existing stone top culvert Bridge No: 197 with RCC boxes between
                   GLY-JCL  stations  on  SC-DHNE  section  has  been  taken  up  and  completed  in  the
                   shadow of mega block at Br No: 74 on 17.05.20.






















                 Rebuilding of Br no: 109 & 196 has also been completed as a part of Doubling of
                   SC-MBNR section by RVNL.