10. Inauguration of Zonal Track Machine Depot (ZTMD) at Cavalry Barracks Station by
Additional Member (Civil Engineering) / Railway Board on 20.02.2021.
Adhering to the instructions of Railway Board for transforming the conventional
maintenance of track into mechanized maintenance, HYB Division took a step forward in
creating necessary infrastructure (ZTMD) at Cavalry Barracks for housing sophisticated
track machines like BCM, SBCM/FRM, Unimat, CSM, Duomatic, BRM, UTV, and DGS.
Some of the key features of this noteworthy asset are detailed as under
Shed/Depot housing two tracks of size 42mx20.5m.
Service building in an area of about 700 Sq.m
A separate block has been provided which accommodates Rest rooms for Staff with
Kitchen, Dining and Toilet facilities
A block for storing heavy duty machines like cutter chains, cutter bars, BCM and FRM
in an area of about 315 Sq.m
For storing machine wise parts as separate entity,4 released rooms have been
provided abutting the main shed/Depot for ease of stacking the parts in the respective
rooms.
An exclusive sub-station and DG set backup of 160kva are provided for uninterrupted
work.
The ZTMD @ CVB is designed to accommodate 4 machines and 4 coaches
simultaneously.
Separate washing area (42 meters) for cleaning of the machine before entering into
the depot.
This ZTMD is located nearby all industrial areas and local workshops which will
reduce the lead time for manufacturing of the machine spares.
IOH of the three divisions HYB division, NED division and SC divisions will be carried
out at ZTMD.
The foundation stone for the project was laid during Nov, 2019.
NI working completed on 10.02.2021.
The Project was stalled for a significant period of time owing to COVID-19 lockdown
(3-4 months), and obtaining permission from Defence Organization, however with all
these constraints the project got completed within 11 months.
Inauguration of Zonal Track Machine Depot (ZTMD) at Cavalry Barracks Station