7.  Canal  Crossing  Works:  Canal Crossing  work between  KEK-DAB  stations  in  SC-MUE
            section is completed duly inserting the girder on 16.05.2020 and further the girder has been
            removed  after completing the box casting work under the track on 29.07.2020.
















                                    RUB Casting work at Canal crossing between KEK-DAB

            8. Increase in Sectional Speeds and New lines.

               a.  Sectional Speeds

                 FM-DHNE Section – CRS sanction received for Raising of sectional speed from 100
                   to 110 Kmph on 02.12.2020 and same has been implemented.

                 SHNR  –GLY  (New  Double  Line)  –  Double  line  commissioned  in  the  month  of
                   Sept‟20 with MPS 75 Kmph and PCE approval received for increasing speed from 75
                   to 100 Kmph on 03.02.2021, same will be implemented by 31.03.2021.


               b.  New Lines

                 Jaklair – Makthal - new line (11 Km) – Commissioned in the month of June‟20, to be
                   taken over by open line from construction.

                 Manoharabad  –  Gajwel  -  new  line  (33  Km)  –  Commissioned  in  the  month  of
                   June‟20, to be taken over by open line from construction.

                 Shadnagar – Gollapalli – Double line (DN Line) (30 Km) – Commissioned in the
                   month of Sept‟20, taken over by open line.

            9. Special Achievements made in Track and Bridge works.

                 Progress of Deep Screening of Plain Track with BCM machine for the year 2020-
                   21 up to Feb-21 is 76 Km.

               i.  During the shadow block of 64 Hrs at Br No: 74 on SC-DHNE section, the Work of
                   Deep Screening with BCM machine has been carried out between stations KCG-FM
                   (DN Line) on SC-DHNE section and a progress of 2.590 Km has been achieved for
                   three days(16.05.20 = 1.260 Km, 17.05.20 = 0.820 Km and 18.05.20 = .510 Km)

               ii.  On 27.12.2020, Division has achieved a progress of 2.700 Km of Deep Screening
                   with BCM machine on a single day (02 Machines), BCM 290 has achieved 1.200  Km
                   and BCM 394 has achieved 1.500 Km. The progress of 2.700 Km in a single day is
                   the best ever progress achieved in the Division.