280 The Complete DESIGN BUILDER
Sample Progress Billing:
Project: ACME Manufacturing
Progress Billing #1
No. Item Amount % Complte Progress Amount
1. General $107140 60% $64000
2. Site Work 118080 20% 23600
3. Concrete 99525 20% 20000
4. Masonry 44155 0 -
5. Metals 59870 0 -
6. Carpentry 13330 0 -
7. Moisture Protection 65040 0 -
8. Doors/Windows 46900 0 -
9. Finishes 77125 0 -
10. Specialties 7650 0 -
11. Building System 180000 0 -
12. Mechanical 92480 0 -
13. Electrical 70000 0 -
Total $982,895 $107600
Deduct 10% holdback (10760)
Balance 96840
Deduct previous payments 0
Progress amount due $96840
Payment due in accordance with the terms of our signed agreement