Sample Schedule of Values:
Schedule of Values Project: ACME Manufacturing
No. Item Amount % Complete Progress Amount
1. General Design fees $50000
Temporaries 22640
Supervision 26400
Miscellaneous 8100
2. Site Work Strip/clear 3600
Excavate 3205
Backfill 14875
Services 15000
Asphalt/curbs 60700
Landscaping 20700
3. Concrete Foundations 41300
Slab on grade 50225
Slab on deck 9000
4. Masonry Interior walls 10000
Exterior face 15000
Brick 17725
5. Metals Structural steel 50870
Miscellaneous 9000
6. Carpentry Rough carpentry 8100
Finish carpentry 1895
Millwork 3290
7.Moisture Protection
Insulation 29240
B/U roof 23800
Siding 10500
Caulking 1200
8.Doors/Windows
Metal doors 4000
Wood doors 4000
Hardware 10700
Aluminum entry 5400
Windows 18000
Overhead doors 4800
9. Finishes Steel stud/drywall 31665
Ceilings 16820
Flooring 18640
Painting 10000
10. Specialties Washroom acc. 7650
Floor grilles 1600
11.Building System
Materials 135000
Erection 45000
12. Mechanical plumbing 14480
hvac 78000
13. Electrical service 8000
distribution 62000
Total $982,895