3.0       PROJECTS

                    3.1  USBRL PROJECT, J&K - So far, we have completed 37.80 km tunnel excavation, out of a total
                         of 46.1 km of the construction of Katra-Dharam Section of Uddhampur-Srinagar-Baramulla
                         Rail Link (USBRL) Project. 8.363 km of tunnel excavation, 6.747 km of Tunnel Lining and
                         3902 MT of launching have been completed during the year.   A turnover of ` 1434 crore
                         (including GST) was achieved from the Project during the year, as compared to ` 1303 crore
                         (including GST) of 2018-19.

                    3.2  Konkan Railway is executing Thermal Power Plant Rail connectivity for NTPC at Kudgi in
                         Karnataka and Gadarwara in Madhya Pradesh at the revised project cost of ` 400 Crore and
                         ` 672 crore resp. During the nancial year 2019-20, NTPC- Kudgi has achieved physical
                         progress of 95% whereas NTPC- Gadarwara has achieved physical progress of 100% (Lead
                         line)  and  90%  (ROR  line).  Coal  loaded  rakes  have  started  to  reach  the  NTPC  plant  in
                         Gadarwara since November 2019.

                    3.3  Route  Electrication  of  Konkan  Railway  Route:  CRS  sanction  has  been  obtained  for
                         introduction of commercial services for carriage of goods and passenger trafc on 25kV Ac
                         traction in Bijoor-Thokur section and electrication work is in progress in other sections of KR
                         route.

                    3.4  Rail connectivity to Vizhinjam International Seaport, Kerala:     An MoU has been signed
                         between the Corporation and Vizhinjam International Seaport Ltd. (VISL) to link the Vizhinjam
                         Seaport with Southern Railway (11 km). The Detailed Project Report (DPR) with an estimated
                         cost of `1032 crore has been submitted to VISL. Southern Railway has conveyed in-principle
                         approval of the project to VISL under 'Non-Governmental Railway (NGR)' Model.

                    3.5  Setting up Rolling Stock Component Factory at Ratnagiri:
                         The  Corporation  is  constructing  the  modern,  Platinum  rated,  green  and  energy  efcient
                         Rolling Stock Component Factory for Central Railway at  Parshuram Lote MIDC (  Additional )
                         to  overhaul  rolling  stock  bogies,  assemblies  and  components.  The  turnkey  contract  for
                         Construction and Project Management services has been awarded. The work of construction
                         of Factory Sheds are underway. The project is expected to be completed by December, 2022.

               4.0  SAFETY WORK

                    4.1  Commissioner of Railway Safety (CRS) carried out Annual Inspection on Konkan Railway
                         route  from  Roha  to  Madgaon  and  Madgaon  to  Suratkal  on  11th  and  12th  April  2019
                         respectively. CRS appreciated the riding quality and other works after the inspection. Overall,
                         the  audit  was  satisfactory. All  the  points  which  required  immediate  attention  have  been
                         attended to.  For certain items, long term planning is required and these are being taken up.