Page 21 - 11394_AEW_XX_XX_PP_A_0003_CO-OP PRE-CONSTRUCTION MANUAL
P. 21

RAM                   Internal PM              External PM                    QS                    Architect                  Format

                 Site identified


             RAM agrees site with LP&P


            RAM produces draft Investment
             Appraisal [IA], legal pack and
                   searches

            RAM instructs Ex.PM to new site                      Ex.PM instructs the Architect                      Architect undertakes Stage 1
                                                                and QS to proceed with Stage 1                          feasibility study

             Request existing hazardous                          Request existing hazardous
               materials information                               materials information

                                                                 Ex.PM sets project plan and
                                                                    issues to team


            Project plan received from Ex.PM  Project plan received from Ex.PM           Project plan received from Ex.PM  Project plan received from Ex.PM  Project plan received from Ex.PM


                                                                 Stage 1 feasibility drawings                        Architect issues Stage 1
                                                                      received                                      feasibility drawings to Ex.PM

                                                                    Attend Site Visit                                  Attend Site Visit


                                                                 Ex.PM reviews and obtains                         Provide 360 photo data following
                                                                agreement from Logistics Team                            Site Visit
                                                                                                                                           Dialogue between Asset
                                                                                                                                           Team and Architect until
                                                                                                                                         Stage 1 feasibility and Asset
                                                                                                                     Architect updates Stage 1   Plan are co-ordinated
                                                                      Updates                  YES                     feasibility drawings
                                                                      required?                                    (and produces scoping drawings
                                                                                                                      for conversions only)
                                                                       NO

                                                                 Pre Construction Support                                                   Format Team produce Asset Plan
                                                                   Document 00 & 01
                                                                                                                     Architect issues the final
                                                                                                                   co-ordinated Stage 1 feasibility
                                                                                                                     (and scoping drawings for   Asset Plan issued to Ex.PM
                                                                                                                    conversions only) to Ex.PM   and Governance
                                                                                                                                                                 NOT AGREED

              Stage 1 feasibility drawings                       Stage 1 feasibility drawings,
            scoping drawings and Asset Plan                     scoping drawings and Asset Plan
                   received                                      received and issued to RAM                                                       Governance
                                                                                                                                                   Approval?

              RAM to review and obtain
               agreement from RLA
                  AGREED                                                                                                                           AGREED

              Zonal analysis undertaken                          Complete Pre Construction
               and issued to Ex.PM                              Support Documents 02, 03 & 04
                                                                and issue project information to
                                                                      the QS


                                                                                          CV1 cost document developed


                                                                 Scheme Approval 1 Pack    Scheme Approval 1 Pack
                                                               CV1, Stage 1 Feasibility drawings,   CV1, Stage 1 Feasibility drawings,
                                                                scoping drawings, Asset Plan &   scoping drawings, Asset Plan &
                                                                    Zonal received          Zonal issued to Ex. PM




                                                                      Review
                                                                    Scheme Approval            YES
                                                                      1 Pack.
                                                                     Are updates
                                                                      required?
                                                                       NO

                                                                 Scheme Approval 1 Pack
                                                               CV1, Stage 1 Feasibility, scoping
                                                                drawings, Asset Plan & Zonal
                                                                submitted for scheme approval

            Scheme aborted or reworked at   Attend Scheme Approval 1   Attend Scheme Approval 1   Attend Scheme Approval 1
                  a later date              Meeting                   Meeting                   Meeting


                          REJECTED     Project reviewed at Scheme    APPROVED              Issue Approved Stage 1 Pack
                                         Approval 1 Meeting                              & CV1 Investment Appraisal [IA]
                                                                                          summary to RAM during the
                                                                                                meeting
                                       Internal PM issues meeting
                                         minutes to the team


             Scheme Approval Meeting                             Scheme Approval Meeting   Scheme Approval Meeting                            Scheme Approval Meeting
                minutes received                                    minutes received         minutes received                                    minutes received


                   RAM
         REJECTED  to review and
                obtain approval
                  from FPB

                 APPROVED

                 FPB Approval                                      Proceed to Stage 2
   16   17   18   19   20   21   22   23   24   25   26