Page 41 - 11394_AEW_XX_XX_PP_A_0003_CO-OP PRE-CONSTRUCTION MANUAL
P. 41
2
2B.4 TCG led project
External PM
Task SLA Issue Available on Standard form
Method I-Site (/)
Procure design team including Structural Engineer, Building Services Engineer and 2 weeks Email -
Planning Consultant
Procure Hazardous Materials Reports (including asbestos) Prior to site visit Email Asbestos Scoping document
Receive complete Principal Designer appointment letter - Email Principal Designer Appointment Letter
Attend Design Team Meeting - - -
Complete and issue Design Team Meeting minutes to the team 1 day Email Design Team Meeting Minutes
Receive Pre-Construction Information from Principal Designer and procure - Email PCI
outstanding PCI as required
Receive planning drawings from the Architect - Email Planning drawings
Notify Format team to review and approve the proposed Advertisements design - Email -
Receive co-ordinated Asset Plan from the Format team - Email -
Instruct Planning Consultant to proceed with submission of application(s) to the 1 day Email -
Local Planning Authority
Receive LPA decisions from Planning Consultant - Email -
Instruct design team to prepare Tender information 1 day Email -
Attend Design Team Meeting - - -
Complete and issue Design Team Meeting minutes to the team 1 day Email Design Team Meeting Minutes
Stage 2 Agree Tender programme 1 day Email - -
-
Attend Tender Review Meeting
-
Complete and issue Tender Review Meeting minutes from External Project Manager 1 day Email Tender Review Meeting Minutes
Undertake Post Tender Qualification process with Quantity Surveyor and Principal 1 week Email -
Contractor
Consult with Quantity Surveyor and make Principal Contractor recommendation 1 day Email -
Receive Scheme Approval 2 package of information from Quantity Surveyor - Email Cost Validation [CV2] cost document
Tender drawings
Review Scheme Approval 2 package of information and notify Quantity Surveyor of 1 day Email -
any required updates prior to submission to Scheme Approval
Attend Scheme Approval 2 meeting and present site with Quantity Surveyor 1 day - -
Receive Scheme Approval 2 meeting minutes from Internal Project Manager - Email Scheme Approval Minutes
Notify RAM to proceed to exchange of contracts if CV2 is less than CV1 1 day Email -
Escalate Cost Validation 2 [CV2] to RAM and Internal Project Manager if CV2 > CV1 1 day Email Cost Validation [CV2] cost document
Notified by RAM / Internal Project Manager to proceed when CV2 costs approved at - Email -
FCEF or by Head of Acquisitions
Notify RAM to proceed with exchange of contracts when CV2 costs approved at - Email -
FCEF or by Head of Acquisitions
Issue Exchange pack (including agreed Tender drawings and PCSD 06) to - Email PCSD 06 – Project Exchange Form
Construction Manager min.1 week prior to Exchange Meeting Tender drawings
Attend Exchange Meeting (on-site for Conversions only) - Email PCSD 06 – Project Exchange Form
Complete and issue Exchange Meeting Minutes from External Project Manager - Email Exchange Meeting Minutes
(Updated PCSD 06 – Project Exchange Form)
2B.4 TCG led project External PM 0.0 11.10.19