        2B.9 TCG led project


        Building Services Engineer








              Task                                                          SLA                Issue        Available on  Standard form
                                                                                               Method       I-Site (/)
              Attend Design Team Meeting                                                       -                         -
              Receive Design Team Meeting minutes from External Project Manager                Email                     Design Team Meeting Minutes
              Prepare drawing information for planning application(s) in conjunction with the   Email                    -
              Architect and Design Team                                                        Email                      -
              Receive instruction from the External Project Manager to prepare Tender drawings /
           Stage 2  information in advance of Design Team Meeting            agreements by Ex.PM  -                      -
                                                                                As per scope
                                                                                                                  
              Attend Design Team Meeting
              Receive Design Team Meeting minutes from External Project Manager                Email                     Design Team Meeting Minutes
              Produce finalized Tender drawings / information in advance of Tender review      Email              
              meeting
              Attend Tender Review Meeting                                                     -                         -
              Receive Tender Review Meeting minutes from External Project Manager              Email                     Tender Review Meeting
              Issue final, co-ordinated Tender drawings / information to Quantity Surveyor     Email                     -


























        2B.10 TCG led project

        Planning Consultant









              Task                                                          SLA                Issue        Available on  Standard form
                                                                                               Method       I-Site (/)

              Attend Design Team Meeting                                    -                  -                         -
              Receive Design Team Meeting minutes from External Project Manager  -             Email                     Design Team Meeting Minutes
           Stage 2  Prepare planning application(s) in conjunction with the Architect and Design Team  - -  Email        - Planning drawings
                                                                                                                  
                                                                                               Email
              Receive planning drawings from the Architect
              Receive instruction from External Project Manager to proceed with submission of   -  Email                 -
              application(s) to the Local Planning Authority
              Issue LPA decisions to RAM, Internal Project Manager, External Project Manager,   1 day  Email             -
              Architect and Principal Designer

























         2B.9   TCG led project                   Building Services Engineer           0.0                                   11.10.19
         2B.10 TCG led project                    Planning Consultant                  0.0                                   11.10.19