        2B.6 TCG led project


        Architect








              Task                                                          SLA                Issue        Available on  Standard form
                                                                                               Method
           Stage 0  Receive instruction from External Project Manager to produce Stage 0 feasibility   -  Email  I-Site (/)   Project Plan (email form)
                                                                                                                  
              study
              Issue Stage 0 feasibility drawing to External Project Manager (and Quantity Surveyor  3 days  Email        Stage 0 Feasibility drawing
              if required)


              Task                                                          SLA                Issue        Available on  Standard form
                                                                                               Method       I-Site (/)
              Receive instruction from External project Manager to proceed with Stage 1 feasibility  -  Email            Project Plan (email form)
              drawings
              Receive Project plan from External Project Manager            -                  Email                     Project Plan (email form)
           Stage 1  Complete and issue Stage 1 feasibility drawings to External Project Manager  1 week  Email           Stage 1 Feasibility drawings
                                                                                                                  
                                                                                                                          -
                                                                                               -
                                                                            -
              Attend site visit with External Project Manager
              Produce 360 photo data following site visit
                                                                                               Email
                                                                            -
              Informed by External Project Manager if Stage 1 feasibility updates are required   1 week  Email           - -
                                                                                                                  
              (multiple options may be required until a preferred solution for the site is identified)
              Co-ordinate Stage 1 feasibility drawings with Asset team and incorporate asset plan  1 week  Email         Stage 1 Feasibility drawings
              Issue final co-ordinated Stage 1 feasibility (and scoping drawings for Conversions   1 week  Email         Stage 1 Feasibility drawings
              only) to External Project Manager                                                                           Scoping drawings
              Task                                                          SLA                Issue        Available on  Standard form
                                                                                               Method       I-Site (/)
              Attend Design Team Meeting                                    -                  -                         -
              Receive Design Team Meeting minutes from External Project Manager  -             Email                     Design Team Meeting Minutes
              Prepare drawing information for planning application(s) in conjunction with the   2 weeks  Email           Planning drawings
              Design Team and issue to RAM, External Project Manager, Quantity Surveyor,
              Principal Designer and Format team
              Receive co-ordinated Asset Plan from the Format team          -                  Email                     -
              Receive LPA decisions from Planning Consultant                -                  Email                     -
           Stage 2  Receive instruction from the External Project Manager to prepare Tender drawings /   -  Email        Tender drawings
              information in advance of Design Team Meeting
              Attend Design Team Meeting                                    -                  -                         -
              Receive Design Team Meeting minutes from External Project Manager  -             Email                     Design Team Meeting Minutes
              Produce finalized Tender drawings / information in advance of Tender review   2 weeks (dependant on   Email    Tender drawings
              meeting                                                       shell complications)
              Attend Tender Review Meeting                                  -                  -                         -
              Receive Tender Review Meeting minutes from External Project Manager  -           Email                     Tender Review Meeting Minutes
              Issue final, co-ordinated Tender drawings / information to Quantity Surveyor  1 week  Email                Tender drawings
              Receive Scheme Approval 2 meeting minutes from Internal Project Manager  -       Email                     Scheme Approval Minutes








































         2B.6   TCG led project                   Architect                            0.0                                   11.10.19
   38   39   40   41   42   43   44   45   46   47   48