Page 44 - 11394_AEW_XX_XX_PP_A_0003_CO-OP PRE-CONSTRUCTION MANUAL
P. 44

2









        2B.7 TCG led project


        Principal Designer








              Task                                                          SLA                Issue        Available on  Standard form
                                                                                               Method       I-Site (/)
              Receive Principal Designer appointment letter from Internal Project Manager  -   Email                     Principal Designer Appointment Letter
              Complete and return Principal Designer Appointment Letter to Internal Project   1 week  Email              Principal Designer Appointment Letter
              Manager and External Project Manager
              Undertake a desktop assessment of survey information and reports. Information   1 week  -                  -
              from desk top review to feed into PCI document
              Attend Design Team Meeting                                    -                  -                         -

              Receive Design Team Meeting minutes from External Project Manager  -             Email                     Design Team Meeting Minutes
           Stage 2  Following design team meeting produce Site Inspection Report identifying site   1 week  Email        Site Inspection Report
              hazards / design feedback, collate PCI and issue to External Project Manager
                                                                                                                          PCI
              Receive planning drawings from the Architect
                                                                            -
                                                                                                                          Planning drawings
                                                                                               Email
              Receive co-ordinated Asset Plan from the Format team          -                  Email                     -
                                                                                                                 
              Receive LPA decisions from Planning Consultant                -                  Email                     -
              Attend Design Team Meeting                                    -                  -                         -
              Receive Design Team Meeting minutes from External Project Manager  -             Email                     Design Team Meeting Minutes
              Attend Tender Review Meeting                                  -                  -                         -

              Receive Tender Review Meeting minutes from External Project Manager  -           Email                     Tender Review Meeting Minutes
              Receive Scheme Approval 2 meeting minutes from Internal Project Manager  -       Email                     Scheme Approval Minutes

















        2B.8 TCG led project

        Structural Engineer









              Task                                                          SLA                Issue        Available on  Standard form
                                                                                               Method       I-Site (/)

              Attend Design Team Meeting                                                       -                         -
              Receive Design Team Meeting minutes from External Project Manager                Email                     Design Team Meeting Minutes
              Prepare drawing information for planning application(s) in conjunction with the   Email                    -
              Architect and Design Team                                                        Email                      -
              Receive instruction from the External Project Manager to prepare Tender drawings /
           Stage 2  information in advance of Design Team Meeting            agreements by Ex.PM  -                      -
                                                                                As per scope
              Attend Design Team Meeting
                                                                                                                  
              Receive Design Team Meeting minutes from External Project Manager                Email                     Design Team Meeting Minutes
              Produce finalized Tender drawings / information in advance of Tender review      Email              
              meeting
              Attend Tender Review Meeting                                                     -                         -
              Receive Tender Review Meeting minutes from External Project Manager              Email                     Tender Review Meeting
              Issue final, co-ordinated Tender drawings / information to Quantity Surveyor     Email                     -
















         2B.7   TCG led project                   Principal Designer                   0.0                                   11.10.19
         2B.8   TCG led project                   Structural Engineer                  0.0                                   11.10.19