6.0 Installation programme TANDEM DRIVE THRU LANES
7.0 Tandem Lane Layout and configuration
When programming a project with SBS DT lane, the following must be considered:
• DT lane must be completed first
• Additional 2 nights work to be allocated for IT team to install new box in managers office to support
POS6
• POS6 work to be complete 2 nights before proposed COD go live date
• All presenter booth works must be complete before the SBS go live date