6.0 Installation programme                                                                                   TANDEM DRIVE THRU LANES
                                                                                                             7.0 Tandem Lane Layout and configuration
When programming a project with SBS DT lane, the following must be considered:

    • DT lane must be completed first
    • Additional 2 nights work to be allocated for IT team to install new box in managers office to support

         POS6
    • POS6 work to be complete 2 nights before proposed COD go live date
    • All presenter booth works must be complete before the SBS go live date