Page 43 - 11394_AEW_XX_XX_PP_A_0003_CO-OP PRE-CONSTRUCTION MANUAL
P. 43
2
2B.6 TCG led project
Architect
Task SLA Issue Available on Standard form
Method
Stage 0 Receive instruction from External Project Manager to produce Stage 0 feasibility - Email I-Site (/) Project Plan (email form)
study
Issue Stage 0 feasibility drawing to External Project Manager (and Quantity Surveyor 3 days Email Stage 0 Feasibility drawing
if required)
Task SLA Issue Available on Standard form
Method I-Site (/)
Receive instruction from External project Manager to proceed with Stage 1 feasibility - Email Project Plan (email form)
drawings
Receive Project plan from External Project Manager - Email Project Plan (email form)
Stage 1 Complete and issue Stage 1 feasibility drawings to External Project Manager 1 week Email Stage 1 Feasibility drawings
-
-
-
Attend site visit with External Project Manager
Produce 360 photo data following site visit
Email
-
Informed by External Project Manager if Stage 1 feasibility updates are required 1 week Email - -
(multiple options may be required until a preferred solution for the site is identified)
Co-ordinate Stage 1 feasibility drawings with Asset team and incorporate asset plan 1 week Email Stage 1 Feasibility drawings
Issue final co-ordinated Stage 1 feasibility (and scoping drawings for Conversions 1 week Email Stage 1 Feasibility drawings
only) to External Project Manager Scoping drawings
Task SLA Issue Available on Standard form
Method I-Site (/)
Attend Design Team Meeting - - -
Receive Design Team Meeting minutes from External Project Manager - Email Design Team Meeting Minutes
Prepare drawing information for planning application(s) in conjunction with the 2 weeks Email Planning drawings
Design Team and issue to RAM, External Project Manager, Quantity Surveyor,
Principal Designer and Format team
Receive co-ordinated Asset Plan from the Format team - Email -
Receive LPA decisions from Planning Consultant - Email -
Stage 2 Receive instruction from the External Project Manager to prepare Tender drawings / - Email Tender drawings
information in advance of Design Team Meeting
Attend Design Team Meeting - - -
Receive Design Team Meeting minutes from External Project Manager - Email Design Team Meeting Minutes
Produce finalized Tender drawings / information in advance of Tender review 2 weeks (dependant on Email Tender drawings
meeting shell complications)
Attend Tender Review Meeting - - -
Receive Tender Review Meeting minutes from External Project Manager - Email Tender Review Meeting Minutes
Issue final, co-ordinated Tender drawings / information to Quantity Surveyor 1 week Email Tender drawings
Receive Scheme Approval 2 meeting minutes from Internal Project Manager - Email Scheme Approval Minutes
2B.6 TCG led project Architect 0.0 11.10.19