Page 40 - 11394_AEW_XX_XX_PP_A_0003_CO-OP PRE-CONSTRUCTION MANUAL
P. 40
2
2B.4 TCG led project
External PM
Task SLA Issue Available on Standard form
Method I-Site (/) Stage 0 instruction (email form)
Notified of Stage 0 marginal site from RAM
Email
-
Stage 0 Instruct Architect (and Quantity Surveyor if Stage 0 cost appraisal required) 1 day Email Project Plan (email form)
Receive Stage 0 feasibility study from Architect (and cost appraisal from Quantity
Surveyor if required) - Email Stage 0 Feasibility drawing
Stage 0 Cost Appraisal
Issue Architects Stage 0 feasibility (and Quantity Surveyor cost appraisal) to RAM 1 day Email Stage 0 Feasibility drawing
Stage 0 Cost Appraisal
Task SLA Issue Available on Standard form
Method I-Site (/)
Notified of Stage 1 non-marginal site from RAM - Email Stage 1 instruction (email form)
Set Project Plan and issue to RAM, Internal Project Manager, Quantity Surveyor, 1 day Email Project Plan (email form)
Architect and Format team
Instruct Architect and Quantity Surveyor to proceed with Stage 1 1 day Email Project Plan (email form)
Receives Stage 1 feasibility drawings from Architect - Email Stage 1 Feasibility drawings
Attend site visit with Architect - - -
Undertake Stage 1 feasibility review and obtain agreement with TCG’s Logistics 1 week Email Stage 1 Feasibility drawings
team
Inform Architect if Stage 1 feasibility updates are required (multiple options may be - Email -
required until a preferred solution for the site is identified)
Complete Pre-Construction Support Documents 00 & 01 and issue to the Format 1 week Email PSCD 00 – Project Info
team as a brief to produce the Asset Plan PSCD 01 – Drawing Governance Support Document [DGSD]
Stage 1 Receive co-ordinated Stage 1 feasibility drawings, Scoping drawings and Asset Plan - - Email Stage 1 Feasibility drawings
Scoping drawings
from the Architect and Format team and issue to the RAM
Zonal Analysis
Email
Receive Zonal Analysis from RAM
Complete PCSD’s 02, 03 and 04 and issue to the Quantity Surveyor along with 1 week Email PCSD 02 – Cost Validation Request Form [CVRF]
current Stage 1 project information for Cost Validation 1 [CV1] to be developed PCSD 03 – Risk Register
PCSD 04 - Key Abnormals Schedule
Stage 1 Feasibility drawings
Zonal Analysis
Receive Scheme Approval 1 package of information from Quantity Surveyor - Email Cost Validation [CV1] cost document
Stage 1 feasibility drawings
Scoping drawings
Zonal Analysis
Review Scheme Approval 1 package of information and notify Quantity Surveyor of 1 day Email -
any required updates prior to submission to Scheme Approval
Attend Scheme Approval 1 meeting and present site with Quantity Surveyor - - -
Receive Scheme Approval 1 meeting minutes from Internal Project Manager - Email Scheme Approval Minutes
Notified by RAM to proceed to Stage 2 following Food Property Board [FPB] - Email -
approval
2B.4 TCG led project External PM 0.0 11.10.19