d) Locally operated Motor points:
Replacement of Manually operated points with locally
operated motor points at SNF yard to ensure safety and to
avoid time loss for clamping and padlocking.
Electrification of Vasavadatta Cement siding (VCSG)/ Seram:
Electrification works on the lead line and in plant was
completed in 2013. Charging could not be done due to
objection from local public. This causing delay in operations
and forced to operate diesel traction in underwire territory.
Provision of individual OHE isolators:
Provision of Individual OHE isolators for each line at 111 stations
to facilitate traffic movement over other lines.
Proposal for extension of trains:
Proposal for extension of trains to ease congestion at TDU and
CT stations with existing lie-over period
Train No. 17664/17663 (NED-TDU-PBN) Express to RC/MALM
Train No. 07659/07660 (SC-CT-SC) MEMU to KLBG
III. GATI SHAKTI TERMINALS 2022-23 Target – 05 GCTs
Potential in rakes Date of
Serving
Siding Commodity per month Commissioning/
Station
Outward Inward TDC
JVRB PSHP Coal 210 - 28-05-2022
MROS STBD Food grains 05 - 20-09-2022
Coal 30
Cement & Clinker 45
PSCS SUH Gypsum 24-09-2022
Clinker Cement 10
05
Ramco- JPTN Limestone 30 - TDC: 30-11-22
TRCL
NTPC Coal & Fly
(PH-I) RDM ash Fly ash 30 Coal 225 TDC: 31-12-22