Page 128 - GM E-booklet 2022-23
P. 128

i.   Coaching:


                        334 Numberr of VPU/VPH ‘s (Indent) were attached to various
                          trains,  in  addtion  to  leased  VPU/VPH’s  up  to  October  –  22
                          and earned an revenue of Rs.4.93crores

                        On day  to day  basis, to clear extra rush of  passengers, 632
                          additional  coaches  were  attached  as  extra  rush,  538
                          coaches were augmented. And also 586 special trains were
                          run for 1738 trips up to the October – 22.
                        Speed of LBH coaches is enhanced to 130kmph, 22 outgoing
                          trains and 16 incoming trains are run with 130kmph regularly.
                        A  total  18.36kms  03rd  line  completed  up  to  October  –  22
                          between BGSF-OPL stations





               4. Operational Infrastructure improvement underway


                       Operational Infrastructure sanctioned:


                   a) PDPL bypass at KZJ end:

                          Sanctioned  3   line  works  between  KZJ-BPQ  under  material
                                             rd
                          modification.(Construction)


                          Status:  Drawings  and  alignment  is  approved.  Estimates

                          prepared.  Needs  to  be  included  for  material  modification
                          and fund allocation.


                   b) Remodeling  of  Jaggayyapeta  Town  (JPTN)  for  enhancing  of
                       CSRs          and  provision  of  “Y”  connectivity  towards  MRCJ

                       siding:
                              Work is sanctioned for three works at JPTN yard under GM-
                          OOT:
                              A. Restoration of Y-Connectivity Rs.2.484 Cr
                              B. Provision of full length loading line Rs.2.49 Cr

                              C. Up-gradation  of  signaling  arrangements  of  Y  –
                    connectivity                        Rs.2.49 Cr.



                          Status: Tenders awarded. LOA issued. TDC- March 2023.