Page 213 - Mines Facilities Plan
P. 213

207
                                             exchangers and control valves to decouple them from the Chiller Plant 6.
                                                   to loop Chiller Plants 6 and 7. Provide engineering analysis of combined
                                                      chiller plant operations (including future Chiller Plant 8). Perform prior to
                                          Provide Brown Hall, Maple Hall and Weaver Towers with dedicated heat
                                                 At Chiller Plants 6 and 7, provide new direct buried 14” CHS/CHR lines















                                                         Research Building 1 coming online. See Appendix 2: Utilities Master Plan for more information.  Necessary precedent projects: None  Chiller Plant 4 Upgrades: Student Innovation Hub Chiller Plant 6: Frontiers Building, Research Building 1  The Plan


















                                                                     Enabled projects:         THE SITE  N/A
                                                                          

























                                          CHILLER PLANT UPGRADES  THE NEED Chiller upgrades and replacements are required in order to accommodate  the addition of the buildings within the Facilities Master Plan. Chiller Plant 4  has an older chiller that will need to be replaced soon. Similarly, Chiller Plant  5 has a chiller that is not operational and should be replaced for redundancy,  back up, and future connections if desired. Additionally, Chiller Plants 5 and 6  require contro