Page 214 - Mines Facilities Plan
P. 214

Mines Parking Structure 1 has been budgeted to have a generator and will
                                                   Resetting building chilled water temperature or shedding chillers may also
                                             not need to be powered by the ISOC generator plant. Other future critical












                                               buildings may also have their own generators.















                                                      be considered. See Appendix 2: Utilities Master Plan for more information.  Necessary precedent projects: None Enabled projects: PowerBlock #1 gensets enables immediate further  construction. PowerBlock #4 gensets and a load shedding strategy enables  full master plan implementation. The ISOC generator upgrades and access should be coordinated with public- private redevelopment of the South Campus Neighborhood.







                                                                            THE SITE
                                                  
                                                         anticipated to exceed the designed maximum capacity of the ISOC generator
                                                                                                  ISOC generator plant. Its critical loads will be backed up by a local UPS
                                                                                     full implementation of the Facilities Master Plan while remaining within the
                                                                                  implement a load shedding strategy. A load shedding strategy would allow
                                                                                               The High Performance Computing Center (HPC) will be shed from the
                                                                         additional gensets in PowerBlock #4 to support full Facilities Master Plan
                                                      construction of all recommended projects, the campus load (12.4 MW) is
                                                                                                        The existing steam plant has its own generator. It does not need to be
                                                 The existing peak demand (6.4 MW) for the campus exceeds the current
                                                   capacity of the South Campus ISOC generator plant (6.2 MW). After the
                                                                                        capacity of the ISOC generator plant. Potential load shedding strategies
                                                                                To accommodate full Facilities Master Plan build out, Mines should also
                                                                      bringing additional buildings online. Mines should install at least three
                                                                   Mines should install two additional gensets in PowerBlock #1 prior to
                                                                                                                      
                                          ELECTRICAL ISOC GENERATOR UPGRADES



                                                                                                           powered by the ISOC generator plant.  Colorado School of Mines Facilities Master Plan















                                              THE NEED      plant.  THE PROJECT  implementation.  include:       and Generator.       208
   209   210   211   212   213   214   215   216   217   218   219