Page 404 - Mines Facilities Plan
P. 404

upgrading the feeders is to put new or existing loads onto a second primary




















                     service from Xcel (item G.2 above). The capacity of the Interruptible Service Option Credit (ISOC) Generator  Plant will need to be increased by installing additional engine-generator sets  (gensets). Two (2) gensets are anticipated to be needed by Summer 2020.  Five (5) additional gensets are anticipated to be needed over the course  of the master plan horizon. In addition, it is anticipated that the load added  during the master plan will eventually exceed the



















                             September 6, 2019. It is important to understand that Xcel’s available capacity
                          on a meeting with Xcel Energy (Xcel), Facilities Management, and SBEC on
                                 rst served                            ISOC CAPACITY  1.25 MW Increase  No increase, but   decreases existing   loads  1.9 MW Increase  No change  No change Note: The years listed in this chart are based on the year buildings are anticipated to start design and therefore the actual work may be performed in subsequent years.
                                   basis, and the opportunity to reserve capacity for future projects is limited
                        options for increasing the capacity available for the campus and is based
                     currently available from Xcel. A table is included below that summarizes
                  The campus electrical power load is projected to exceed the capacity
                                 rst come, fi and expensive. As a result, SBEC recommends that the available capacity be   




                                is reallocated to new loads and new customers on a fi






                                        reviewed with Xcel on an annual basis. The campus electrical power load as part of the master plan is projected  to exceed the capacity of two (2) of the campus medium voltage feeders.  However, the projected load includes a 15 percent safety factor for new  buildings. As a result, the projected load is conservative, and the actual load  from the anticipated future buildings may be lower. The actual peak demand  for the campus should be monitor











               ELECTRICAL                                              YEAR  2020  2021  2023  Opt. 1  2023  Opt. 2  2027  Opt. 1  2027  Opt. 2  398
   399   400   401   402   403   404   405   406   407   408   409