Page 11 - Bernardon Response to RFP-Project Pegisis
P. 11
www.bernardon.com
High Level Project Schedule
Upon receiving Notice to Proceed, we will meet and collaborate with JLL - PDS and Project stakeholders to establish
a mutually agreeable schedule that meets the goals of the project. Bernardon’s Team of professionals allows us to
provide the necessary resources and support to complete the project in a timely manner; moreover, we have the
flexibility to work with your team to modify our delivery schedule if the need should arise. The following project
schedule outlines an approach that would lead to great success.
2021 2022
PROJECT PEGISIS
AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT
Project Schedule
1 Notice to Proceed
8/15
2 Programming/Space Planning
8/16 - 9/17
2a Approval of Program *
9/21
A
3 Schematic Design (SD)
9/20 - 10/15
3a Approval of SD 10/15 *
3b SD Construction Cost Estimate
10/15 - 10/29
Pre-Purchase Package for Electrical Gear and Air Handling
3c
Equipment 10/25
4 Design Development (DD)
10/18 - 11/24
4a DD Construction Cost Estimate
11/24 - 12/08
4b Approval of DD *
12/10
4c Apply for Building Permit *
12/20
4d Pre-purchase Package for Lab Casework and Fume Hoods 12/19
5 Construction Documents
12/13 - 1/28/2022
6 Bidding 1/31 - 2/28
6a Bid Award *
2/2 - 2/4
6b Mobilize and begin Construction *
2/7
7 Substantial Completion
7/15
7a Punchlist and Commissioning
7/18 - 8/12
8 Building Occupancy
8/15/2022
BERNARDON | Response to Request for Proposal for Architectural and Engineering Services
JLL - PDS | Project Pegisis | July 20, 2021 Page 10