FOUNDRY PRODUCTION

               The governing board should include: the head of the governing board - the head of the
        enterprise or his first deputy, members of the governing board: heads of the main divisions of
        the enterprise, heads of subsidiaries (dependent) enterprises on the topic being introduced, the
        project manager.
               For direct and operational management of the implementation of the project, an executive
        board is usually formed, the main tasks of which may be:
        ● implementation of operational planning and ongoing control over the implementation of the
        project;
        ● ensuring methodological, organizational and technological unity of design solutions;
        ● determination of uniform project standards (each stage of the project corresponds to a package
        of documents and a register of tasks that need to be solved);
        ● initiating the creation of working groups to address important substantive issues;
        ● management of working groups;
        ● introduction of control over the quality of work execution at each stage;
        ● preparation of messages, reports, reports, questions, formation of an agenda for meetings of
        the governing council.
               The executive board includes: the head of the executive board (project manager - chairman),
                                heads of project  and working  groups, technical  manager of the project
                                implementation.  In  accordance  with the  orders  of  the  executive  board,
                                                             working groups are  formed  (a team  to ensure
                                                             the logistics of engineering) to conduct analysis;
                                                             develop methods and mechanisms for solving the
                                                             problem,  and  implement  recommendations  for
                                                             improving the project. It seems expedient to create