ADTM Risks & Risk Mitigation

                                   th
               (Ver 1.6, Last Update 16  July 2018)

               The purpose of this document is to identify all Risks involved during the Life Cycle of the
               Software Project.

               The document is prepared based on Vendors experience with Clients and is aligned to the
               ADTM.

               Having identified the Risks, the Client and the Vendor have to jointly work out a plan to
               overcome such Risks.

               Risks once mitigated prevent project failure, delayed projects and cost over runs.


               This document covers business continuity planning to some extent and the formulation of the
               IT policy.

               Risks                        Impact                       Solution
               Non appointment of the       No one is really             Appoint Steering Committee
               Steering committee or        responsible and Vendor has  after consulting all Senior
               appointing employees with  no authority over              Management
               no real commitment to the    Clients  Staff to implement
               IT project                   project

               During the Gap Analysis      Project Delayed due to lack  The Steering Committee
               the key operational staff    of information & thereafter  should ensure all relevant
               are not consulted            software modifications and  employees participate
                                            re testing needed.           especially operational staff
                                                                         familiar with the manual
                                                                         processes

               Client not signing the Gap   Vendor will develop          However busy the client maybe
               Analysis                     Software based on            it is essential that he takes the
                                            requirements that the        time to meet the Vendor’s
                                            Client has not agreed or     development  team and sign off
                                            possibly not looked at. This  the Gap Analysis
                                            is similar to building a
                                            house which an architect
                                            has designed but the Client
                                            has not agreed on the
                                            design.


               No Data Back ups             In case of data losses due   The IT policy must define the
                                            to any reason the Client     frequency of Data backups
                                            will have no means to        (most Organizations perform it
                                            continue with the system.    daily) and keep backups
                                            This can lead even to a      outside the Office.
                                            complete halt in business



               © Datama tion Systems (Pvt) Ltd. – 2019(Version 3.12)                                                             Page 8 of 11