Page 179 - ADMINISTRATIVE MANUAL
P. 179

163

 ACTIVITY   BY CONTRACT                BY ADMINISTRATION
 OFFICE/UNIT   UNDERTAKING   OFFICE/UNIT                  UNDERTAKING


    Board of   Approves winning bidder
    Regents
        Approves Contract

       Issues Notice of Award & require
    Office of the   submission of Performance Bond

    President
       Signs Contract

       Issues Notice to Commence Work


       2. Inform Board of Regent
       Issues Memorandum detailing
    Board of   Technical Staff of Univ. Infra      Issues Memorandum detailing
 PROJECT   Regents   Office at the Construction Site      one (1) Technical Staff of the
 INPLEMENTATION     who shall be responsible in      Campus Infra Office at the
 Supervision      supervising the ongoing   Office of the   Campus where the project/s

    construction, to wit:   President            is/are undertaken who shall be
 Office of the                                   responsible in supervising the
 President   a.1 To see to it that the progress   ongoing project/s, to wit:
 of work is in accordance with the               a.1 To see to it that the
 Program of Work, Plans &                        progress of work is in

 Specification.                                  accordance with the Work
 a.2 To see to it that the materials             Program
 used are in accordance with the                 a.2 To see to it that the
 plans & specifications                          materials used are in
 a.3 To initiate the issuance of                 accordance with the plans and
 certifications as to percentage of              specification
 accomplishment in accordance                    a.3 To regularly report to the

 with the Contract                               ED through the Architect the
                                                 progress of work, copy
                                                 furnished, President