       NISOC ramps up southern Iranian production





        IRAN             THE National Iranian South Oil Co. (NISOC)  production increase, is ready, with three of the
                         reported this week that it had increased oil pro-  first six contracts completer. Meanwhile, two
                         duction by 30% during the previous six months.  wells will soon increase production capacity at
                           Speaking to the official Islamic Republic News  the Lali oilfield.
                         Agency (IRNA), NISOC’s managing director   He said: “By implementing production
                         Ahmad Mohammadi said that expects output to  increase and maintenance plans, a total of
                         grow by a further 10% during the current Iranian  300,000 barrels of oil will be added to the produc-
                         calendar year, which started this week.  tion of south oilfields, and production decline by
                           He said that the company intends to increase  the same amount will be prevented in these 28
                         output to 300,000 barrels per day (bpd) across  reservoirs.” Around 70% of the project is focused
                         the 28 fields its operates and to maintain that  on the southwestern Khuzestan Province with
                         level of production capacity.        the remainder covering neighbouring provinces.
                           Mohammadi noted that contracts for six   In early March, the company kicked off engi-
                         packages had been awarded for the first phase of  neering, procurement and construction (EPC),
                         this plan, pegging subsurface progress at these  and engineering, procurement and drilling
                         projects at 50%. Surface work was estimated at  (EPD) work for the development of the onshore
                         around 20%.                          Siahmakan oilfield under a project that should
                           Meanwhile, contracts have also been signed  expand production by around 10,000 bpd.
                         for a further 19 packages with only tenders   NISOC awarded a contract to expand pro-
                         remaining, for the Gachsaran and Qala-e-Nar  duction at Siahmakan to Pasargad Energy
                         fields, though these are nearing conclusion.  Development Co. in May 2020, covering field
                           Mohammadi added that work on the  development through an integrated EPD/EPC
                         Nargesi expansion project, covering a 5,000-bpd  package.™