Page 13 - MEOG Week 12 2021
P. 13

MEOG                                            TENDERS                                               MEOG


       KOC pushes back deadline for pipe bids





        KUWAIT           STATE-OWNED Kuwait Oil Co. (KOC) last  rising to 230,000 bpd by 2030/31, with heavy oil
                         week extended the deadline for bidding for a  from the nearby Umm Niqa field seen climbing
                         contract to install an oil pipeline at an oilfield in  first to 50,000 bpd and then to 80,000 bpd over
                         the north of the country.            the same period. A fourth phase would then see
                           Company sources were quoted by local, Ara-  Ratqa’s production lifted to 325,000 bpd, while
                         bic-language media as saying that the final date  the final phase envisages output from the two
                         for bids to be submitted for the $150mn project  fields totalling 430,000 bpd.
                         to transport oil produced from the Umm Niqa   Kuwait has been attempting to maintain
                         oilfield had been pushed back, but did not spec-  highly ambitious capacity targets of 4mn bpd by
                         ify when bidding would now close.    the end of this year and 4.75mn bpd by the end of
                           It noted that the scope of the work includes  2040, up from the current 3.1-3.2mn bpd. In late
                         the installation of flow lines for oil producing  2019, the 2020 target was reported to have been
                         wells, a closure system for flow lines, reinforced  pushed back to 2040.
                         plastic pipelines for water, hot water cocks, well-
                         head connections, extending existing heads and  Tank maintenance
                         manifolds and carbon steel pipelines, as well as  Local media also reported this week that KOC
                         welding work.                        will soon tender for maintenance work to be car-
                           The original deadline had been March 8 fol-  ried out at oil storage tanks located at fields in the
                         lowing the call for tenders in February.  south and west, and north of the country.
                           The source said that pre-qualified bidders   Following an announcement by the Supreme
                         included seven local firms as well as companies  Procurement Committee at KOC’s parent
                         from China, India, Indonesia, Italy, Lebanon and  Kuwait Petroleum Corp. (KPC), 11 companies
                         Qatar.                               have been pre-qualified to bid for the work,
                           Umm Niqa is one of two fields being devel-  including 10 local firms and one from Lebanon.
                         oped under the Lower Fars Heavy Oil Project,
                         alongside South Ratqa. The broader Ratqa asset  Bad press
                         was discovered in the late 1970s, but efforts to  Meanwhile, KOC has come under scrutiny after
                         develop the field were largely stifled until the  contractors participating in one of the compa-
                         UK’s Petrofac was finally awarded a $4.2bn engi-  ny’s 2020 tenders complained about a lack of
                         neering, procurement & construction (EPC)  transparency and questioned the fairness of
                         contract to execute the first phase in early 2015.  competition.
                         This called for production of 60,000 barrels per   Arab Times quoted the company, which
                         day (bpd) by 2020.                   wished to remain anonymous, as saying: “The
                           Output from the two fields under the project  participants in this tender had submitted bank
                         reached a first phase plateau of 75,000 bpd fol-  guarantees, which had to be extended. This led
                         lowing the start of operations in February last  them to bear additional burdens. We wonder if
                         year.                                it is reasonable for a company of the size of KOC,
                           However, in September, KOC was reported to  after the closing of the tender and having been
                         have cancelled a project to drill 11 wells as part  informed of the prices, to change its awarding
                         of the country’s efforts to expand the production  strategy. We demand the regulatory authori-
                         of heavy oil. Citing senior company sources, the  ties intervene to stop any practices or potential
                         local Al-Rai newspaper said that the $400mn  manipulation in awarding this tender.”
                         contract had already been awarded to an interna-  The company said that the tender had been
                         tional company, but that it was yet to be signed.  pending for more than six months, with the
                           According to KOC’s original plan, by 2026/27  delay leading to a slowing in efforts to increase
                         output from Ratqa would grow to 120,000 bpd,  production.™

























       Week 12   24•March•2021                  www. NEWSBASE .com                                             P13
   8   9   10   11   12   13   14   15   16   17   18