Page 70 - HIL Operatives Training Manual V4 16022024_Neat
P. 70

O P E R A T I V E S   T R A I N I N G   M A N U A L                           V E R S I O N   4

               Moving a tower

               1.  Towers should only be moved with the utmost caution. Before moving, ensure the route is
                   clear of any obstructions, both at ground level and overhead.
               2.  Never attempt to move a tower with people or materials still on it.

               3.  Ensure the tower height is reduced to 4mtrs or below before moving.

               4.  Stabilisers should be left in position, and raised no more than 25mm from the ground

               5.  Move the tower only by applying manual effort at the base of the tower. The tower is not
                   designed to be lifted or suspended. Always inspect the tower after moving and before use.

               6.  Never throw equipment from the tower, either lower it with a rope or by hand.

               7.  Any  components  found  to  be  damaged  should  be  isolated,  tagged  and  reported  to
                   someone in authority to either have them repaired or removed from service.

               If all of the above controls are followed, then the risk of injury to persons has been
               brought down to as low as is reasonably practicable.
               18.6  Scaffolding/Staging

                   •  Foreman,  Managers  or  Project  Engineers  carrying  out  work  that  cannot  safely  be
                      performed  from  ground  level  are  to  assess  the  need  for  access  scaffolding  or
                      alternative means of access (e.g., ladders, tower platform / scaffold). Where scaffolding
                      / staging is required then it is for the supervisor concerned to ensure that adequate and
                      safe staging is provided and used.
                   •  The design of the staging is to conform to the general requirement of applicable British
                      Standards and erected in accordance with the relevant statutory requirement.
                   •  Only persons who have been trained and authorised are permitted to erect, alter or
                      dismantle staging, including self-erect or suspended stages.
                   •  Where  sub  -contractors  are  requested  to  provide  and  erect  tubular  staging,  formal
                      arrangements must be determined for the staging to be inspected at intervals specified
                      under the statutory regulations.
                   •  It is the responsibility of all Foremen, Managers or Engineers to ensure that all statutory
                      checks are carried out on any scaffolding erected for the use of their staff and to take
                      immediate action if defects are found or suspected. Consideration must also be given
                      to stopping all persons using the scaffolding if personnel are likely to be put at risk by
                      the noted defects.
                   •  The  Construction  Design  and  Management  Regulation  2015  requires  that  all
                      scaffolding is inspected by a competent person on a regular basis under the following
                      circumstances:
                   a)  Before being taken into use for the first time.
                   b)  After any substantial addition, dismantling or other alteration.
                   c)  At regular intervals not exceeding 7 days since the last inspection.
                   d)  After any event likely to have affected it’s strength or stability. (e.g. adverse weather
                      conditions)

               Once the inspection is complete and the scaffolding declared safe to use, a certificate is issued
               which should ideally be displayed on the scaffolding itself and a copy kept in the site office.
               The certificate must be available on site and produced on demand from a HSE Inspector.








                                                    Page 69 of 142
   65   66   67   68   69   70   71   72   73   74   75