Ref  : CM-DFH4-2014-1
                                                    BEAZLEY                   Issue : 1

                                               DFH 4 Series Spacecraft        Date : 28 Sept 2014
                                                                                                Page 32 of 38






                CHINASAT 18               Observation                    Comment /Assessment         Cri
                               Page 60.
                                DFH-4E qualification units qualification
                                 timeline
                                     o  All the units qualification will be
                                        finished in Oct.2014
                                     o  DFH-4 engineering model and
                                        thermal model qualification    The development plan indicates that the
                                        timeline                        customer requirements are not yet
                   Project           o  The thermal model qualification  defined.
                  Schedule              has been finished in Dec. 2013    The contract is under negotiation.
                                     o  The engineering model          One can conclude that this presentation is
                                        qualification will be finished in  part of the negotiations and the design is
                Development             Oct. 2014                       not mature yet.
                                     o  CHINASAT-18 project current     It is premature to assess the design and
                 plan & test            status                         identify risks with the information
                                         The customer requirements are
                                     o                                  provided to date.
                                        just confirmed.
                                         The contract is under negotiation
                                     o
                                        AIT plan is almost the same as
                                     o
                                        DFH-4 satellite and the specified
                                        schedule will be provided after the
                                        contract formally signed.
                                          Table 10-d Chinasat 18 technical assessment








            9.1 CHINASAT 18 DFH 4E TECHNICAL ASSESSMENT SUMMARY



            Based on the above, one can conclude:

                  The Chinasat 18, DFH 4E design is not mature because:
                       o  The contract is under negotiation
                       o  The customer requirements are not frozen
                       o  The schedule is not established
                  There is some doubts on the power increase up to 15 KW, (making use of the said qualified ETCA PCU) and
                   the implication on various subsystems (EPS, Solar array, power handling and dissipation on N & S panels,
                   thermal subsystem, payload, including antenna and its mechanism).
                  As for other spacecrafts the categorization and the base for qualification could be challenged.

            As of today, with the information provided and the status of the program (performances requirements not yet defined), is
            it almost impossible to provide you any assessment of the performances / and in-orbit risk items.













             This document is proprietary of BEAZLEY© and must be treated on a confidential basis. It may be used solely by BEAZLEY, use or reproduction, of the document and the
                                  Contained therein, for any other purposes without BEAZLEY written consent is prohibited.
   29   30   31   32   33   34   35   36   37   38