Renovation, renovation, renovation



                 equipment, which was brought above
                 ground for easy access. The best   FIGURE 9 Design image of planned   FIGURE 10 One of six block valve
                 available techniques for assessment   completed block valve site  installations completed by NARC
                 were undertaken at the Cambridge
                 tee, leading to the installation of
                 three electro-hydraulic actuators,
                 improving our environmental
                 footprint as well as meeting safety
                 and operational requirements.
                   Part of NARC’s innovation remit was
                 to assess the condition of Feeder 3
                 valves removed from the ground as
                 part of the replacement block valve
                 works, having provided over 45 years
                 of service. Two contractors were
                 commissioned with random samples   FIGURE 11 Top previous Cambridge tee pit,   FIGURE 12 Guestwick AGI, during a 24 hour
                 taken to conduct material analysis   bottom, New Cambridge tee    continuous working period in order to
                 that has been fed back into our needs                             secure UK gas supplies
                 case and justification models.
                   The innovation project for
                 glassfiber reinforced plastic (GRP)
                 pipe supports has been successfully
                 progressed for use in 2018. A
                 prototype was manufactured, crush
                 testing has confirmed its vertical load
                 capability and a design specification
                 has been produced. Installation is
                 scheduled for later this year.
                   During summer 2017, surveys and
                 conceptual design reports were
                 completed for five feeder sections
                 and five compressor stations/large
                 AGIs to inform the work scope of our                              FIGURE 13 Design image, utilising BIM, of
                 second year of delivery (NARC 2).                                 Brisley site works delivered for NARC 2 in
                 Three CDP meetings over one month                                 2018
                 successfully agreed the NARC 2
                 scope. NARC 2’s site construction is
                 nearing completion, with four new
                 installation rebuilds, five separate
                 national feeder pipe-throughs and
                 over 10 installations revalidated
                 through P/11 inspections.
                   Current declared efficiencies for
                 NARC this annum are £9 million, of
                 which £4 million came from utilising   The following innovations are
                 pipe-through solutions instead of   planned for incorporation into NARC
                 full site replacements and       2 during 2018:                   ■  NARC is currently reviewing shallow
                 coordinating multiple works under   ■  Continuing the strategy of using high   dig techniques for vent and sealant
                 single pipeline shutdowns. The rest   performance gearboxes on locally-  line replacement on block valves for
                 was due to competitive tender,     operated valves, but further     utilisation suitable for the campaign.
                 contractor efficiencies, and       developing the use of these    ■  Following learnings from corrosion
                 recompression efficiencies.        gearboxes to replace remote valve   of the V/6 specified welded vent
                   Business information modelling   actuation.                       and sealant line supports, NARC
                 (BIM) utilisation has continued with   ■  Planning the first ever site   has implemented a design change
                 great success for NARC 2 construction   installation of GRP supports which,   with our 2018 long lead valve
                 works, not just with the creation of   due to our smart split body design,   supplier to ensure ball valves are
                 modular designs, but especially in the   enables the support to be   supplied with plastic anti-corrosion
                 negotiation and agreement to date of   withdrawn from the pipeline and   clips. These are currently being
                 several difficult outage works with   re-used, it allows easier and cheaper   manufactured in Germany. ■
                 third parties. It embeds the temporary   withdrawal for pipeline inspection,
                 works design with the permanent    it’s lightweight and will not corrode,   ■ For more information, contact
                 works, increasing installation efficiency   has a design life of 40 years and is   author Chris Bates via email at
                 and safety, reducing risk and cost.  cheaper to purchase.         christopher.j.bates@nationalgrid.com