Understanding the process of EIA, EMP and where WMP is located within the process and
             procedure in preparing the EIA is in Chapter 2. Note that Wildlife Impact Study (WIS) is a part of
               EIA and WMP is a part of EMP. Without approval of WIS by PERHILITAN, the EIA may not be
               approved, and without the approval of the WMP by PERHILITAN, the EMP report may not be
                      approved by DOE, thereby preventing a proposed project from commencing.



                                                      Proposed
                                                       Project




                                              Screening by Project Proponent
                                1. Is the project subject to section 34A, First and Second Schedule?
                                    2. Is the project in line with Development Plan & Policies?


                                    First Schedule Activities
                                                            Second Schedule Activities
                         PRE-SUBMISSION OF EIA  REPORT STAGE  Procedure) Submission of TOR  Procedure)  Revised TOR
                                                             (12 Weeks EIA Reviewing
                                    (5 Weeks EIA Reviewing
                                                       Scoping
                                                                                      Process
                                           (Formulation of Terms of Reference)
                                                                                       Ends

                                                                                    not submitted


                                                                                        TOR
                                                       TORAC            NO            Revised.
                                                       MEETING                       Re-submited
                                                                                       in time





                                                                   YES
                                                                                    If Conformed
                                          First Schedule    Submission of EIA Report
                                                              Second Schedule
                         DURING SUBMISSION OF  EIA REPORT STAGE  Rejected  EIATRC MEETING  Public Display  Rejected
                                    Submission of EIA Report

                                                                     TRC
                                                                                         EIA
                                              TRC
                                                                                        Report
                                                                          YES

                                         AND DECISION
                                   NO
                                                                   AND DECISION
                                         MAKING (STATE
                                                                    MAKING (DG)
                                           DIRECTION     Approved  EIATRC MEETING     NO
                                            OR DG)
                                                            YES
                                                Approved With Conditions
                                                -Submission of EMP/WMP    Notes:
                                                    -Review Meeting
                         POST SUBMISSION OF  EIA REPORT STAGE  -Performance Monitoring (PM)  TORAC: Terms of Reference Adequacy
                                                                          TRC: DOE Technical Review Committee
                                                  - Presentation of COA
                                                                          (Team of DOE officer at DOE State or
                                                                          Headquarters)
                                                     -Execution Plan
                                                                          Check
                                                                          RAC: Report Adequacy Check
                                               -Compliance Monitoring (CM)
                                                                          EIA TRC: EIA Technical Review
                                                                          Committee at DOE State or
                                                 -Impact Monitoring (IM)
                                                                          Headquarters
                                                                          GAs: Government Agencies
                                                                          AIs: Appointed Individual on case
                                                      -Investigation
                                                                          by case based and may include Non-
                                                -Penalty/corrective measure
                                                                          Government Organization (NGOs)
             Figure 1.1: General Overview of EIA Procedure in Malaysia with insertion of WMP as part of EMP
           04       GUIDANCE DOCUMENT FOR PREPARATION AND SUBMISSION OF WILDLIFE
                    MANAGEMENT PLAN (WMP) IN ENVIRONMENTAL IMPACT ASSESSMENT (EIA)