“We choose the design-build process because it           One of these challenges came from mother nature
      gives us the maximum amount of input right there         herself in the form of record rainfall topping 20
      at the table. We have everyone seated around the         inches in just four months. The 30 415-foot-deep
      table,” reflects John Zeswitz, the Executive Vice        geothermal wells, elevator shaft, basement, and
      President of Lancaster Bible College at the time         foundations all required significant excavation
      of construction. “It gives us the opportunity to         work under extreme conditions.
      understand the impact of some of the choices and
      discussions that we’re having.”                          In addition, several large sinkholes were uncovered
                                                               and made worse by the excessive rains. In
      By having the key players involved in the initial        response, the team had to quickly relocate
      planning phase, Lancaster Bible College could            some of the geothermal wells and add sinkhole
      communicate their vision for the project as the          remediation into the project schedule.
      design-build team worked together to find the
      best path towards making that vision a reality.          Because of the collaborative approach of the
                                                               design-build method, the team was able to quickly
      Unlike a design-bid-build or construction manager        adjust to these challenges and move the project
      at risk scenario, the project was designed with          forward to its successful completion.
      input from the construction team. This more
      collaborative approach leads to a more realistic         “The design-build gets much more of a
      plan. And having a solid plan gives the team more        collaborative conversation going earlier. And
      bandwidth to deal with the inevitable, unforeseen        we found that that yields trust, and trust goes a
      challenges that can arise once construction kicked       long way in the construction of a facility,” shares
      off.                                                     Zeswitz.




















     IS DESIGN-BUILD RIGHT FOR MY CONSTRUCTION PROJECT?


      Overall, design-build can benefit projects of any        However, the best decisions are ones that are
      size and budget. This method establishes early           made when all options are considered. For more
      collaboration in the project’s planning and design       information on the other project delivery methods,
      phases which leads to fewer problems down the            check out this blog. You can also take our short
      road. That often translates to lower project costs       quiz that will help you determine which project
      and quicker project schedules.                           delivery method is best for your project!

      The streamlined communication flow and
      reduction in both burden and risk for the owner
      make the process easier and more efficient.