Mooreglen Holsteins Dairy Barn Tuckersmith Pork Loose Sow and
Mooretown, Ontario Farrowing Facility
Mooreglen Holsteins Dairy Facility consisted of Seaforth, Ontario
a pre-engineered steel structure combined with
traditional framed components. This large 105’ x This multi-barn project commenced in the summer
484’ 4-row free stall barn with a double 10 parlour of 2016 with construction of a breeding facility
and a 20’ x 54’ milkhouse also incorporated a flush consisting of two 498’ barns connected by a 50’
transfer system to handle manure and washwater connection link containing the office/generator/
for the facility. equipment room. The 91’ x 498 loose sow barn is
designed with an 8’ pit below and the 81’ x 498’
Construction commenced in June, 2017 and the new farrowing barn designed with a 4’ pit below the
dairy facility was in operation by the Spring of 2018. barn. This project was completed and the barn was
in use by June, 2018.
Green Alda Farms Dairy Facility Webb Creek Acres Broiler Barn
Plattsville, Ontario Thames Centre, Ontario
With work commenced in the Spring of 2017, the 64’ x 265’ Broiler Facility with a 15’ x 64’
Hofstetter Family constructed a 72’ x 268’ 3-row free Utility/Generator/Biosecurity area at the
stall dairy facility equipped with a milking robot, a front entrance of the barn. The rear of the
32’ x 45’ calf area and a 27’ x 38’ milkhouse. Design barn contained an open 64’ x 50’ solid
also includes a perimeter feed alley and manure manure storage pad. Initial construction
scrapes to a cross gutter to a piston pump that commenced in the Spring of 2018 with the
transfers manure to a new 95’ diameter by 13.5’ barn completed by the Summer of 2018.
deep liquid manure storage tank.