Table 26 the overall plan of the team for the project
Task Duration Start date Finish date
Initiation 10/7/2019 20/9/2019
Starting the project 70 10/7/2019 7/9/2019
Set the plan for the project Day 7/9/2019 8/9/2019
Gather information about the project 8/9/2019 19/9/2019
Prepare the Business case 19/9/2019 20/9/2019
Planning 20/9/2019 8/10/2019
Business case 18 20/9/2019 24/9/2019
Project charter
Day 01/10//2019 06/10/2019
Quality Function Diagram (QFD) 07/10/2019 08/10/2019
Execution 01/12/2019 25/04/2020
Design and drawing
Calculation 01/12/2019 25/12/2019
Manufacturing the parts
152 25/12/2019 25/12/2019
Day 01/02/2020 08/03/2020
Assemble the car 08/03/2020 15/04/2020
1st run test 15/04/2020 25/04/2020
Closure 25 25/03/2020 25/04/2020
Day 20/02/2019 20/02/2019
Check final report 25/02/2019 25/02/2020
Complete the manufacturing 25/02/2020 25/02/2020
process 10/3/2020 15/3/2020
Prepare the final report 15/3/2020 25/4/2020
Prepare the final presentation
Final presentation and submitting
final project