                       28.1.1   Installation
                                Install dual drains at least 1 meter (3 feet) apart and at the lowest point in the
                                RECREATIONAL WATER FACILITY. Ensure that there are no intermediate
                                drain isolation valves on the lines between the drains (Figure 19a). In a channel
                                system (an UNBLOCKABLE DRAIN), a grate-type cover would be attached to
                                the channel (Figure 19b).











































                       28.1.2   ASME A112.19.8M-2007
                                When fully assembled and installed, SUCTION FITTINGS must prevent the
                                potential for body, digit, or limb entrapment in accordance with ASME
                                A112.19.8M-2007.

                       28.1.3   Stamped and Certified
                                Manufactured drain covers and SUCTION FITTINGS must be stamped and
                                certified in accordance with the standards set forth in ASME A112.19.8-2007.


                       28.1.4   Design of Field Fabricated Covers and Fittings
                                The design of custom/shipyard constructed (field fabricated) drain covers and
                                SUCTION FITTINGS must be fully specified by a registered design
                                professional in accordance with ASME A112.19.8-2007. The specifications
                                must fully address cover/grate loadings; durability; hair, finger, and limb