Quantity Surveying: Guideline for Quantity Surveyor Chapter 6
Damage to property of contractors
Injury, death or damage resulting from vibration or failure / weakness
temporary structure
Any liability arising from food poisoning, dirt from sewage, fire or explosion,
environmental pollution and the like.
Period of coverage are :
According to the contract for PWD 203 clause 33 public liabilities insurance
covering the entire period of construction and defects liability period and
added 14 days and 3 month.
Additional 14 days for the SO provides a schedule of defects and 3 months
to repair the defect
If the extended construction period, the insurance period should be
extended in accordance with an additional time period.
Defect Liability
Construction period period Repairing Defect
12 months 3 months
Defect 14 days
Period of insurance
Figure 6.11 : Period of Insurance