Quantity Surveying: Guideline for Quantity Surveyor                                                         Chapter 6


                               Damage to property of contractors

                               Injury, death or damage resulting from vibration or failure / weakness
                                temporary structure
                               Any liability arising from food poisoning, dirt from sewage, fire or explosion,

                                environmental pollution and the like.

                   Period of coverage are :
                               According to the contract for PWD 203 clause 33 public liabilities insurance

                                covering  the  entire  period  of  construction  and  defects  liability  period  and
                                added 14 days and 3 month.
                               Additional 14 days for the SO provides a schedule of defects and 3 months

                                to repair the defect
                               If  the  extended  construction  period,  the  insurance  period  should  be

                                extended in accordance with an additional time period.




                                                                 Defect Liability
                            Construction period                      period               Repairing Defect


                                                                     12 months                3 months

                                                                               Defect 14 days



                                                          Period of insurance



                                              Figure 6.11 : Period of Insurance