Professional Practice: Guideline for Quantity Surveyor Chapter 3
Cost plus target fee
The use of this method required a target fee to be set for the project prior to the signing
of the contract. Have incentive factor to contractor to reduce or minimize project cost if
the actual cost is lower than targeted cost.
However if the actual cost is higher than targeted cost, contractor payment will be
deducted based on the agreed fee/percentage
Table 3.4: Calculation of Cost Plus Target Fee