Page 94 - BASIC GUIDELINE FOR QS
P. 94

Professional Practice: Guideline for Quantity Surveyor                                                     Chapter 3


                   Cost plus fixed fee
                   The  contractor’s  profit  is  predetermined  by  agreeing  a  fee  for  the  work  before  the

                   commencement of the project.

                                                               Amount                  Total Amount
                         Cost Plus Fixed Fee
                                                                 (RM)                       (RM)


                       1.  Labour Cost                          39,000
                       2.  Material Cost                        59,000

                       3.  Sub Con Work Cost                    10,000
                       4.  Machinery and plant Cost             2,000                     110,000
                         Add fixed fee                                                     15,000


                   Project Cost                                                           125,000


                                        Table 3.2:  Calculation of Cost plus Fixed Fee


                   Cost plus percentage
                   The contractor is paid the cost of labour, materials, plant, subcontractors and overheads,
                   and the sum is added a percentage to cover profits. The percentage is agreed at the

                   outset of the project.

                                                              Amount                     Total Amount
                        Cost Plus Percentage
                                                                (RM)                          (RM)


                   1.  Labour Cost                             40,000
                          Add 25%                              10,000                        50,000
                   2.   Material Cost                          60,000

                         Add 10%                                6,000                        66,000
                   3.   Sub Con Work Cost                      10,000
                         Add 5%                                  500                         10,500

                   4.   Machinery and plant Cost                2,000
                         Add 10%                                 200                         2,200



                         Project Cost                                                       128,700


                                       Table 3.3: Calculation of Cost Plus Percentage