Page 94 - BASIC GUIDELINE FOR QS
P. 94
Professional Practice: Guideline for Quantity Surveyor Chapter 3
Cost plus fixed fee
The contractor’s profit is predetermined by agreeing a fee for the work before the
commencement of the project.
Amount Total Amount
Cost Plus Fixed Fee
(RM) (RM)
1. Labour Cost 39,000
2. Material Cost 59,000
3. Sub Con Work Cost 10,000
4. Machinery and plant Cost 2,000 110,000
Add fixed fee 15,000
Project Cost 125,000
Table 3.2: Calculation of Cost plus Fixed Fee
Cost plus percentage
The contractor is paid the cost of labour, materials, plant, subcontractors and overheads,
and the sum is added a percentage to cover profits. The percentage is agreed at the
outset of the project.
Amount Total Amount
Cost Plus Percentage
(RM) (RM)
1. Labour Cost 40,000
Add 25% 10,000 50,000
2. Material Cost 60,000
Add 10% 6,000 66,000
3. Sub Con Work Cost 10,000
Add 5% 500 10,500
4. Machinery and plant Cost 2,000
Add 10% 200 2,200
Project Cost 128,700
Table 3.3: Calculation of Cost Plus Percentage
83