Page 92 - BASIC GUIDELINE FOR QS
P. 92

Professional Practice: Guideline for Quantity Surveyor                                                     Chapter 3


                   There are two main features of the traditional method:


                             i.   Bill of quantities procurement method

                            ii.   Drawing and specification (Lump Sum)



                   i.     Bill of quantities procurement method


                   Bills of quantities procurement method is a contract document comprising a list of
                   the  materials  required  for  the  works  and  their  estimated  quantities,  produced  by  the

                   quantity  surveyor.  The  contractor  tenders  against  this  document,  stating  his  price  for
                   supplying and installing each of the materials.


                          The total of the contractor's prices, added to his prices for the various items in the

                   Preliminaries, forms the contract sum. The contract sum cannot be varied just because
                   the actual quantities differ from those in the bills of quantities, so the contractor must
                   satisfy  himself  that  the  quantities  shown  are  at  least  approximately  correct.  The

                   employer must provide drawings and bills of quantities to specify the quantity and quality
                   of work.


                   ii.    Drawing and Specification (lump sum) procurement method


                   With  lump  sum  contracts,  the  contract  sum  is  determined  before  construction  work  is
                   started. A final contract amount is agreed to and the work begins. This type of contract

                   priced on the basis of drawings and usually another document, such as a specification or
                   work schedules.


                          The employer must provide drawings together with a description of works, and

                   either  a  specification  or  work  schedules  at  tender  stage.  The  project  is  generally  not
                   complex  enough to  require  bills  of quantities. The  price  and  payment  structure  of the
                   contract is based on a lump sum with monthly interim payments.



                          A lump sum approach in terms of design, quality and cost is relatively low risk
                   procurement option for a client, however the time required for the project overall is likely
                   to be longer than other procurement methods.






                                                             81
   87   88   89   90   91   92   93   94   95   96   97