Other development costs include such items as professional fees, developer
               overheads, finance costs and developer margin.

               5.2.1 Construction costs

               I  have referred  to the RICS’s BCIS  (Building Cost  Information Service) as
               the industry standard.


               This  provides  tender  prices  (average)  for  a  range  of  development  types
               including estate housing and flats.

               I have adopted these baseline costs.  To these I have made the following
               adjustments:

                 Added 15% for external works and site infrastructure;
                 Allowed for a 20% adjustment for gross to net for flats (BCIS are quoted
                   gross and the appraisal is set up on a net basis);
                 Adjusted for location – Sussex.

               The calculations are set out in the table on the following page:
















               The Council. In their Dixon and Searle report, have commented on the costs
               and  have  established  their  own  –  at,  I  believe,  £2,124  per  square  metre
               taking into account baseline, location factor, net to gross and contingency.

               This looks low, and is explained in part by adopted a lower than industry
               standard  allowance  for  external  and  infrastructure  (at  10%).    It  is
               understood  that  a  5%  contingency  is  allowed  by  D  and  S,  which  I  have
               included.