Compensation

             Corgan proposes to provide the Services identified above as a Lump Sum fee, billed on a monthly basis,
             based on percentage complete of each phase of the project. Fees quoted below are based on estimates of
             professional time required at each phase and for the estimated durations noted above. Reimbursable project
             expenses (document printing, travel, mileage, parking fees, delivery and courier) will be in addition to fees for
             professional services and will be invoiced at 1.10 times our direct cost.


             BASE PROJECT SCOPE
             Project Kick-Off                                $7,500
             Discovery (Visioning and Programming)           $24,500
             Concept Planning                                $38,000
             Strategic Planning                              $42,000
             Phasing Plans                                                         $15,500
             Subtotal – Base Project Scope                   $127,500



             ESTIMATED REIMBURSABLES
             Subtotal – Estimated Reimbursables              $5,000



             TOTAL BASIC SERVICES
             Total Basic Services (with reimbursables)       $132,500


             SUPPLEMENTAL SERVICES

             Supplemental Visioning Sessions (per meeting)   $2,500
             Supplemental Programming Meetings (per meeting)  $550
             Workplace Standards Playbook                    $18,500
             Workforce Assessment Survey                     $35,000
             Test Fits                                       $0.15/USF
             Future Work Virtual Experience                  $18,000
             MEP Campus Systems Assessment                   $18,500
             Campus Strategy Video                           TBD