9.  All of the following are true regarding code-of-accounts identifiers except for which

         one?

         A.  These are unique numbers for each component on the WBS.

         B.  They are documented in the WBS dictionary.

         C.  They are tied to the organization’s chart of accounts.

         D.  They are assigned to the resources who are associated with the work package
              level.

    10.  Your team has already created a WBS for the ABC product launch project. You are
         kicking off phase 2 of this project, which is the product development phase. Which

         of the following is an example of what might appear in the second level of your
         project’s WBS?

         A.  ABC Product Launch Project

         B.  Project deliverables

         C.  Project phases

         D.  Activities

    11.  Which element is not a component or function of the scope management plan?

         A.  Describes the deliverables acceptance criteria

         B.  Describes how scope changes will be handled


         C.  Describes the procedures for preparing the scope statement

         D.  Describes the procedures for preparing the WBS

    12.  This involves changing the project or product scope without considering the
         impacts it will have to the project schedule, budget, and resources.

         A.  Change request

         B.  Scope creep

         C.  Stakeholder/management directive

         D.  Quality deficiency

    13.  There are three primary constraints on most all projects. Your customer, or project

         sponsor, will stipulate which of the three is the most important to them. Which
         three are the typical constraints found on the majority of projects? Choose three.

         A.  Budget

         B.  Team members

         C.  Scope

         D.  Quality