4. Which of the following are components of a scope statement? Choose three.
A. General project approach
B. Project description
C. Assumptions and constraints
D. Exclusions
E. Stakeholder list
F. High-level milestones
G. Change request process
5. A WBS is created using a technique called decomposition. What is decomposition?
A. Matching resources with deliverables
B. Breaking down the project deliverables into smaller, more manageable
components
C. Estimating the cost of each individual deliverable
D. Creating a detailed to-do list for each work package
6. What is the lowest level of the WBS?
A. Work package
B. Level 5
C. Milestone
D. Activities
7. Which of the following describes influences?
A. Influences can impact, change, or create a new constraint.
B. Scope creep is an example of an influence.
C. Change request is an influence.
D. Interaction between constraints is an example of an influence.
E. All of the above
F. A, B, D
8. Which of the following is not a benefit of a WBS?
A. A WBS is an excellent tool for team building.
B. A WBS helps prevent critical work from being overlooked.
C. A WBS can become a template for future projects.
D. A WBS can be used to describe how the deliverables will be validated.