Page 139 - Project+
        P. 139
     E.  Time
         F.  Sponsors and stakeholders
         G.  Scope management plan
    14.  Your project is underway, and a key stakeholder has submitted a change request.
         After further investigation, you discover some scope creep has also occurred on the
         project. These are examples of which of the following?
         A.  Constraints
         B.  Assumptions
         C.  Influences
         D.  Dependencies
    15.  Which term describes a characteristic of the scope planning (and other Planning)
         processes?
         A.  Looping
         B.  Iterative
         C.  Ongoing
         D.  Repetitive
    16.  Your project is nearing completion of the first phase. Your key stakeholder for this
         phase reminds you that she will not accept the deliverable unless it measures 3
         centimeters exactly. If the measurements are off, phase 2 will be delayed, and the
         entire project will be at risk. This is an example of which of the following?
         A.  Acceptance criteria
         B.  Change request
         C.  Stability of scope
         D.  Product scope description
    17.  Elements of the project that are not listed on the WBS are considered what? Choose
         two.
         A.  Work that will be completed in a future phase of the project
         B.  Exclusions from scope
         C.  They are considered scope creep.
         D.  They are not considered part of the project.
         E.  They are considered change requests.
    18.  You’re developing a scope statement for a customer request. A couple of the
         elements that the customer wants could be difficult to accomplish, but after
                                                            139





