Page 140 - Project+
P. 140
consulting with the project team, you think they can be done. These elements are
not included in the product description. What should you do?
A. Include these elements in the scope document, trusting your project team to
deliver.
B. Include these elements in the scope document, denoting them as a concern, and
document how the issues were resolved.
C. Discuss the problem elements with the project sponsor and the customer.
Obtain sponsor sign-off.
D. Note the elements in the exclusions section of the scope statement, and state
that they’ll be included in phase 2.
19. As you decompose the WBS, you discover a requirement that wasn’t listed in the
requirements section of the scope statement. This requirement is essential to a
successful project because it details industry standard measurements that your
team must comply with in order to complete the deliverable. Which of the following
is true regarding this scenario?
A. This is an example of a constraint.
B. This is an example of an influence.
C. This is an example of an assumption.
D. This is an example of a dependency.
20. You’re developing the scope statement for a new project. What project phase are
you in?
A. Initiating
B. Planning
C. Executing
D. Controlling